2022 Bond Projects
Project Update
BSD's goal is to complete a structural evaluation of Five Oaks Middle School. This means designing new structural elements at the footing, wall and roof level to increase the building's ability to withstand a seismic event, per the District's goals.
The District will negotiate a guaranteed maximum price within a couple of months.
Main goal: Replace the roof, which has been leaking.
The project is currently in the Design Development phase, and CIDA. Architects should be issuing design development drawings on November 7.
BSD will be reviewing existing conditions with the design team in October and will be issuing their schematic design cost estimate.
Modernization
Stage Improvements
Seismic Upgrades
Structural Reinforcements
Technology
One-to-One Chromebooks
Networking Upgrades
Deferred Maintenance
Roof Replacement
Security & Other Equipment
Additional Security Cameras
Replacement School Buses
Water Bottle Filling Stations
Completed 2014 Bond Projects
To review the projects that were completed at Five Oaks Middle School as part of the 2014-2022 Bond, visit the 2014-2022 Bond webpage.