October 2020

ACMA

October 2020 - Science classroom casework and epoxy counters at ACMA.

Work Completed

  • Site asphalt
  • Masonry
  • Roof
  • Windows

Work Underway

  • Planting
  • Casework
  • Carpet
  • Irrigation
  • Sidewalks
  • Concrete polishing
  • Tilework
  • Exterior metal paneling
  • Interior painting

Substantial Completion: August 2021

General Contractor: Robinson Construction
Architect: DLR Group