February 2021

ACMA

February 2021 - Polished concrete stairway in commons area at ACMA.

Work Completed 

  • Concrete polishing
  • Masonry
  • Roofing
  • Windows
  • Sheetrock
  • Solar panels
  • Fencing
  • Carpet
  • Sidewalks
  • Metal paneling
  • Tilework

Work Underway

  • Planting
  • Casework
  • Irrigation
  • Lighting
  • TVs and projector installation
  • Ceiling tiles
  • Interior painting touchup
  • Cleanup

Substantial Completion: August 2021

General Contractor: Robinson Construction
Architect: DLR Group